Update - Island Dunes -- Thursday, Sept. 30
Progress is being made at Oceanside I. Most of the building has water and electricity, and the elevator is running (most of the time). Ted is trying to get the air conditioning running. Much of the cleanup effort has focused on getting the sand out of the lobby and common areas. There was as much as 4 feet of sand in the lobby.
There has not yet been time to go to each unit to assess damage, but they may be able to start on that tomorrow. Several units are known to have damage becasue their shutters were blown in. At least one unit had a window blown in even though the shutters were not damaged! We'll try to get more detailed information out tomorrow.