Friday, October 22, 2004

Update - Oceanside I-- Friday, Oct. 22

Some updates on Oceanside I:

Most of the demolition work in the common areas has been completed. The damaged equipment and wallboard has been removed. Areas exposed to the outside have been boarded up, and the interior work areas are also boarded up. The storage rooms have been completely gutted, and are cleaned and ready for rebuilding. However, no rebuilding will be started on any of the lower areas until the dunes are stabilized and we can have some assurance the areas will not be flooded again (see the related posting below). Repairs are, however, in progress for all units that were damaged in the storms.

There will be a board meeting next Tuesday night to approve a general contractor for the building for all future repairs. Please plan to attend if you are in town.

0 Comments:

Post a Comment

<< Home